Presidio Coastal Trail (Completed Spring 2012)

The Lincoln/Merchant Connector Stairs and Behind the Golden Gate Overlook

Behind the Golden Gate Overlook everything is at finished grade and Barth's surfacing has been put down. Erosion control buttons up the area.

Box steps with Barth's surfacing has been put in leading up to the connector stairs at the Lincoln and Merchant Intersection.

Golden Bay Construction has built the battered walls at the connector stairs and are now building the stairs between the walls. Campbell Grading Inc. backfilled and put in erosion control around these battered walls. Planting in this area will begin shortly.